Seudónimo Seudónimo
  • 03-05-2017
  • Mathematics
contestada

it takes 3,600 person hours to complete a project.how many weeks will it take a team of 15 people to complete the job if each person works 8 hours 5 days a week?

Respuesta :

connorkerns connorkerns
  • 03-05-2017
21 hope this helps slmvsdv
Answer Link

Otras preguntas

find the greatest common factor of the following monomials 49a4b3 21a4b5
Please help me with the answers
The new Hazard Communication Standards provide teachers and students the right to __________ chemical hazards.
Factorise x(6x - 5y) - 4(6x - 5y)^2
How do you do this TwT
Help me please………………………
PLS HELP ME ON THIS QUESTION I WIL MARK YOU AS BRAINLIEST IF YOU KNOW THE ANSWER!! The number of rare coins a coin collector owns is considered ________ data. A
Help me please………………………
(b) State the unit of volume in S.I. system and define it. 4.​
Activity 1.2.1: Sentence completion Complete the following sentences by choosing the correct word or phrase from the alternatives given. 1. I need a quiet place