It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

What is step 2 in the problem-solving process? A. Do the work. B. Write down the facts and figures. C. Read the problem. D. Find a relationship be
what is the y intercept for 2x-5y=15
In a survey, 520 people, or 50%, said they attended a movie at least once a month. How many people were surveyed?
What ability does IT lack? A. the ability to reason B. the ability to get angry C. the ability to communicate D. the ability to love
______ typically feel slippery when touched.
During a total lunar eclipse, the moon a. moves into earth's umbra. b. moves outside earth's shadow. c. moves into earth's penumbra. d. moves into the s
the graph shows a volume of ice cubes versus temperature in degrees celsius. which statement if false
A car depreciated by 25% during the first year. If the car was purchased for $28,000, what is the car worth today?
Can someone please help me with part B?
Please help me with this question