A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Subtract: 6lb 4oz - 2lb 10oz
factoring-16w²+50wz-21z²  please help me solve
what are at least 5 general PowerPoint guidelines that's you find useful and provide an example of how you would use each in real life setting
What Should I Know About Nigeria?
Solve for x/4-x+2/6=x/3
what did Benjamin franklin feel strong about
what did Benjamin franklin feel strong about
information about tigers
True or false. If a line L1has equation y = mx + b, where m and b are constants with m ≠ 0, then an equation of a line L2 perpendicular to L1 has the form y = -
Im not quite sure how to answer this question... A 1000kg rocket is moving at a constant velocity in deep space; it is moving at 40 meters/second when its burne